Scheduling reality
What we can do today, and what needs a calendar
Two trucks are held back every weekday morning for same-day work. The rest of the board is booked out — and we'd rather tell you that than promise a Thursday we can't keep.
- Same day: dead circuits, tripping breakers, GFCI faults, open neutrals, dead outlets, smoke/CO interconnect failures.
- 3–6 business days: Level 2 EV charger on a dedicated 240V circuit, whole-home Type 2 surge device, can-light retrofits, bath fans, hot tub disconnects.
- 2–3 weeks: 100A-to-200A service upgrades — the wait is Avista's meter-pull coordination, not ours. Install day itself runs 6–8 hours.
- 4–8 weeks: full and partial rewires, knob-and-tube remediation, generator plus transfer switch. Walk-through and written scope first, always.
- Insurance deadline? Say so on the phone. Knob-and-tube non-renewal letters get scoped within 72 hours.